Goals of Exercise 7
In Exercise Seven we split the lab up into two different parts. The first part of the lab, the goal was to be able write a Python Script (see blog post below to view python script). After running the script we were left with 41 mines to use for part two.

In part two of the lab, we were to use Network Analysis tools to figure out the distance from the mines to the closest rail terminal, using roadways. Finally, after accumulating the routes, we were to find how much it cost each individual county to have these trucks running on the roads (equation further down on blog).

Data sets we will be using include, Wisconsin County Map, ESRI street map of the United States, and the points we found in the previous part.

Lastly, in order to calculate the cost we used the equation of 50 trucks per year drive down the roads at 2.2 cents per mile. The trucks will also have to make the trip back from the train rail to the sand mine. In order to calculate this I used an equation of 100 trucks times the 2.2 cents per mile.

Methods

The model above shows the step by step process to figure out the routes needed for the mines to get to the closest rail terminal. 
This involved using the streets layer, and the network analysis to find the closest facility. Next we had to add the mines we found in the previous part of the lab and again find the closest facility. Lastly we added the rail terminals and found the closest facility, and solved. Next we selected our data, this would be the routes we made, and copied the features, and thus we could have them saved as the final results.


The above image is the final result of the above blog post, after a select by attribute was applied in order to see how many counties were effected by routes.

From there we would move on to the next part of the exercise, trying to figure out how much money it cost each county.



This model shows the steps taken in order to calculate the total cost per county. It involved creating many new fields, such as miles and kilometers fields (kilometers field was created to make the conversion easier since the data was saved in meters). The last field we calculated was created using the equation mentioned above in order to calculate the final cost. Using the cost data we were able to create the graphs seen below.


After calculating the cost per county and summarizing the data we were able to create a chart of how much it was costing each county to have trucks run on their roads. 



The two images above, top side, shows the table used to calculate the cost and how much it is going to cost to each county, the image on the bottom was a graph made on excel to show the cost in a lowest to highest price. 

CONCLUSION

Overall we were able to see which counties were receiving the most traffic and cost on them. The two highest I found in my data were Chippewa and Wood Counties. While Trempealeau County having the most mines on the map, they were all relatively close to the rail stations.